ERCOT · Matagorda County, Texas
A 52 MWac Earth Mount Solar PV project now in construction — fully permitted, fully interconnected, and fully contracted with LyondellBasell. 100% of membership interests offered for acquisition between mechanical completion and COD in November 2026.
The opportunity
Project Bravo reaches the market with every critical-path development item executed — site control, interconnection, permitting, offtake, financing, and procurement. The project is now under construction — with Erthos delivering as EPC — and is offered to a buyer to own at COD.
Fully executed lease and gen-tie easement — optioned March 2022, amended through January 2025.
ERCOT SGIA with AEP Texas executed Q4 2023, amended & restated October 2024 and January 2026. $7M security posted.
Fully funded through construction, with a qualified tax-equity provider.
All major equipment procured — modules, inverters, MV — with no outstanding risks to schedule.
20-year Private Use Network PPA with Equistar Chemicals, LP (LyondellBasell) — investment-grade credit with parent guarantee.
Construction-ready. All permits in hand; no outstanding conditions to start of work.
30% ITC plus 10% energy community adder. Safe harbor achieved.
20-year fixed-price O&M by Erthos Energy Services with a 100% performance guarantee.
Project specifications
The offering
Acquisition to close between mechanical completion and COD. The project transfers fully contracted, fully financed through construction, and wrapped by Erthos for 20 years of operations.
Offtake
Bravo delivers energy under a 20-year Private Use Network (PUN) PPA with Equistar Chemicals, LP — a LyondellBasell company — serving the adjacent Matagorda polymers complex behind the Conoco 138 kV substation.
The facility has been approved in ERCOT's Quarterly Stability Assessment for Q3 2026 synchronization.
Location & grid
AEP Texas · busbar settlement · 50 MWac injection rights. Gen-tie easement executed.
~2,100-acre HDPE polymers complex off TX-60 south of Bay City — the PUN offtaker's load.
Matagorda County qualifies under the IRA energy community rules. Qualification documentation in the data room.
Field-proven & resilient
The Texas Gulf Coast is exactly where Earth Mount Solar's advantages matter most. Laying modules on the ground eliminates the wind, hail, and flood failure modes that make single-axis trackers hard to insure and finance in a hurricane-and-hail region — so an Erthos plant is a fundamentally more resilient asset to own here. And because a Bravo block is a design Erthos has already built and operated, bringing it to this scale is the replication of a proven system — borne out by an independent engineer and a third-party technology assessment.
With no torque tube, Earth Mount has no torsional-galloping failure mode — the instability that has damaged trackers at gusts under 60 mph and that leaves them unrated for Category 5. CPP measured no movement to the tunnel's 215 mph maximum. The site's structural code requirement is 137 mph (ASCE 7-16); the system clears it with wide margin.
Bravo doubles the standard 2.0 mm module glass to 4.0 mm — tested to withstand ice balls up to 85 mm, roughly equivalent to 5″ (127 mm) natural hail. Protection is static: there is no stow mode, weather feed, or mechanical actuation to fail before a storm, which materially eases convective-storm insurability.
The independent engineer confirms no project structures sit within a FEMA special flood hazard area; no floodplain permit is required. Modules lie flat with engineered weep holes, so stormwater drains straight to the soil — no elevated racking to dam debris or concentrate scour. Erthos wires the array with TE SOLARLOK 2.0 gel-filled connectors rated to IP68 (1 m, 1,000+ hrs) — versus one hour for standard MC4 connectors.
Independently verified
An independent P50 of 122.9 GWh and P90 of 118.1 GWh — corroborating the project's own ~124 GWh estimate.
Earth Mount Solar's energy model validated against real operating data; structural and wind reports found compliant with the IBC and ASCE 7.
The independent IE report supported an approval for non-recourse long-term debt — permits complete, with no fatal flaws identified.
Technology · in depth
New to Earth Mount Solar PV? Rotate, zoom, and inspect the interactive model below — the same system now being installed at Bravo — then read through the engineering Q&A.
An Erthos plant is built from repeating blocks — arrays group into islands, islands into a block, and each block feeds one 4.4 MVA power conditioning system (PCS). Bravo is 12 such blocks of 550 W Imperial Star glass/glass modules on Sungrow 4.4 MVA PCS units, per Site Plan SP100.
{{ fq.a }}
Sale process
Interested parties
Qualified investors and IPPs receive a management call, then a portal password and confidentiality acceptance for full diligence access.
{{ formErr }}
By submitting you consent to be contacted regarding this transaction.
Sam Barton has been notified and will reach out to schedule a management call. A portal password follows the call.
Or email sam.barton@erthos.com directlyThe private portal contains the confidential project detail, 40-year financials, and the diligence data room.
Incorrect password. Passwords are case-sensitive.
Passwords are issued following a management call — request access above.
Access to the private portal is conditioned on your acceptance of the confidentiality provision below, entered into with Erthos, Inc. (“Erthos”), which is facilitating the transaction.
Placeholder — to be conformed to the Erthos standard MNDA1. Confidential Information. All information made available in the private sections of this portal — including project documents, agreements, financial models, technical materials, and the terms of any proposed transaction (collectively, the "Confidential Information") — is made available by Erthos, Inc. and is confidential and proprietary to Erthos and its affiliates.
2. Use. You will use Confidential Information solely to evaluate a potential acquisition of the membership interests of Industrial Bravo Project LLC (the "Transaction") and for no other purpose.
3. Non-disclosure. You will not disclose, reproduce, or distribute Confidential Information except to your directors, officers, employees, and professional advisers who need it to evaluate the Transaction and who are bound by confidentiality obligations at least as protective as these.
4. Return / destruction. Upon request, you will promptly return or destroy all Confidential Information and certify the same.
5. No license; no offer. No license or other rights are granted. The portal does not constitute an offer, and any Transaction will occur only under definitive written agreements.
6. Term. These obligations survive for two (2) years from acceptance, and run in favor of Erthos, Inc. and its affiliates. [Governing law, remedies, and remaining provisions per the executed MNDA.]
{{ ackErr }}
{{ whoLine }} — the private portal is unlocked below.